Year: 2026
Type: Structural Steel
Location: Hudson Road, New Plymouth
Customer: M Powick

Project Description: Supply and install new structural steel for twin workshops.

Prework and Planning: Strong planning with the client using his 3D model of the design to ensure all aspects of the build go flawlessly. With a very tight site for delivery and storage of steel assemblies onsite, a staged delivery plan was required to ensure all assemblies were placed at the correct location allowing the crane access and reach to install them.

Result: A very smooth install with happy client and engineer.